Six hours to complete the modular house hoisting!

Six hours to complete the modular house hoisting! GS Housing build the Home of Builders in Xiongan New Area with Beijing Urban Construction Group.

1

1st building of 2nd Camp, Xiongan New Area Builder’s Home, Mr. Feng-General Manager of GS Housing Engineering Company, led the construction team to complete the modular house hoisting task.

2
3 Project preparation team

Until to April 27th,2020, the hoisting of more than 3,000 integrated houses in Xiongan Builder's Home No.2 Camp Project has been completed, the supporting buildings, office buildings and outdoor paving were on going.

4
5 slogan of Epidemic prevention and control, safety production

When GS housing received the task of Xiongan New Area builders home project, Xiongan Office of  GS Housing quickly organized the company's various departments, and established a special team to coordinate various departments, including sales, design, production, installation and construction, and all depts. promptly put into the preparatory work for the project. Fight the epidemic in a good spirit and prepare for the construction of the camp.

6
7

During the epidemic period, GS Housing attaches great importance to epidemic prevention and control work, and highly coordinates with Party A to promote epidemic prevention and control work everyday on the project site .

8
9

Set up the special epidemic monitors and safety officers to measure and record the people’s body temperature every day, monitor people to wear the mask at all times, and disinfect the project site at regular time every day to effectively ensure the safe production and safe construction.

10
11

Project background
Project: 2nd Camp, Xiongan New Area Builder’s Home,
Project location: Xiongan New Area ,China
Project QTY:1143 set modular house

12
13

Project scale:
2nd Camp, Xiongan New Area Builder’s Home, covers 550000 ㎡,more than 3000 sets modular houses at all, the project will be build as a comprehensive living community with facilities,include office buildings, dormitories, living facilities, fire station and water station, it can meet about 6500 builders and 600 managers live and work.

14
15

GS housing assigned comprehensive technical engineers stationed at the project site,Mr.Gao  has been resident on the project site for more than a month. He has been constantly communicating with Party A's technical staff on technical difficulties and discussing the technical realization method of the Builder's House, constantly improving the technical points of the project drawings. He witnessed the gradual transformation of Builder's House assembly camp from a model to a resident house.

16 discuss the assemble details
17

Tianjin Factory, North China Base of GS Housing, quickly organizes production when receiving the production task, all-round support the house production, delivery, logistics, Actively mobilizing all departments of the factory, coordinating the layout and delivering goods on time it is an important backbone for the successful installation of Xiongan Builder's Home.

18
19

GS housing has an independent engineering company, is the rear protection of GS housing. It undertakes all the construction tasks of the project. There are 17 teams, all of whom have received professional training. During the construction, they constantly improve the awareness of safe construction, civilized construction and green construction. And require themselves to ensure the progress, quality, service of the project with GS housing installation concept "GS Housing product, must be high quality".

20
21

More than 1000 set flat-packed container houses assembly tasks on site, Mr Tao - the installment leader, leads an excellent installment team to finish the task.
When the flat-packed container house arrived at the project site, the assembly team quickly claimed their installation tasks and put into the installation work.

22
23

Mr. Tao arranged the assembly work and led the workers to fight day and night. During this period, he slept in his car at night and did not dare to go too far away from the project site in case of any emergency. His suntanned face and ringing mobile phone are the signs of devotion to the construction of the Xiongan New Area Builder’s Home.

24
25

Time is tight and volume is large in the hoisting site. After complete the house assembly, Mr. Feng calmly organized the team to number the modular houses one by one, and hoist the house according to the number, and arranged double cranes in the left and right of site to ensure the hoisting quality and speed. There are many managers at the assembly site to direct the process and eliminate deviation.
The workers dressed in new work clothes, worked hard and completed the hoisting task with high quality.

26
27

Another team led by project supervisor Pang installed the water&electrical, window&door, house interior decoration...step by step.

28
29

Together with Beijing Urban Construction Group, GS Housing builds a home for builders. To be an eternal camp emissary with an assembly mind. For all the builders of xiong'an New District, we will create a warm home!


Post time: 19-08-21